Washington halts Seattle tunnel project over safety concerns

SEATTLE — Washington transportation officials and Gov. Jay Inslee on Thursday halted all digging by Seattle’s tunnel-boring machine until the contractor determines what caused a large sinkhole to form over the area where the machine was operating.

“I have great concerns regarding public safety if the contractor were to move forward without addressing the root causes of this sinkhole,” Inslee said during a news conference. “We must continue to protect the public safety.”

The sinkhole, measuring 35 feet long, 20 to 25 feet wide and 15 feet deep, appeared Tuesday night. The contractor, Seattle Tunnel Partners, filled it with concrete, according to transportation officials. Officials also cited an accident on Tuesday when a barge carrying excavated soil began to tip and dropped material into the water. The spill posed a hazard to the tunnel workers and the public, officials said in a letter to the contractor.

Transportation Secretary Lynn Peterson said they ordered the work stoppage “to ensure that the contractor has the right protocols in place to proceed with their work safely.”

The tunnel-boring machine called Bertha will not be allowed to resume until the contractor’s analysis and work plans satisfy the state’s experts, she said.

A tunnel along Seattle waterfront was the plan of choice to replace the Alaskan Way Viaduct after it was damaged in a 2001 earthquake. But Bertha broke down about two years ago and only recently resumed operations after repairs were completed.

“I want to remind everyone that replacing the viaduct is critical to public safety,” Peterson said. “The tunneling work must proceed, but it must proceed safely.”

State officials conducted a manual survey of the viaduct and found no new movement, both Peterson and Inslee said.

“I want to stress the very reason the Legislature proceeded with this project originally was to tear down the seismically vulnerable viaduct and fundamentally ensure public safety,” Inslee said.

This was the second delay this week.

Digging in the tunnel was stopped on Tuesday after a barge carrying soil that was pulled from the tunnel began to lean to one side and spilled some of its load into Elliott Bay before drifting into a nearby pier. In order to prevent damage to the conveyor system, workers released the barge from its moorage at Terminal 46. That’s when some of the soil spilled into the bay.

Tunnel excavation was put on hold while the contractor inspected the terminal and pier for damage.

The original completion date for the new Seattle tunnel was the fall of 2015. When the machine started moving again, Project Manager Chris Dixon said they’ll finish the tunneling phase by January 2017 and the double-decker highway project will open to traffic in April 2018 — almost three years late.

It’s not known how the latest work stoppage will affect those plans.

___

AP reporter Rachel La Corte contributed from Olympia, Washington.

____

Follow Martha Bellisle at https://twitter.com/marthabellisle . Her work can be found at http://bigstory.ap.org/journalist/martha-bellisle .

More in News

The Alaska Department of Transportation and Public Facilities drops explosives via helicopter to trigger controlled avalanches above Thane Road in February 2023. (Clarise Larson / Juneau Empire file photo)
DOT&PF reduces avalanche hazard over Thane, Mount Juneau remains a risk

They flew over the snowpack above Thane in a helicopter Thursday to test for controlled avalanche.

A whale tale sculpture on the downtown docks glows on New Year’s Day 2026. (Mari Kanagy / Juneau Empire)
January’s First Friday: Here’s what to see

Juneau Arts Humanities Council announced a preview of community events on First Friday.

Mendenhall Glacier, Governor Mike Dunleavy, and glacial outburst flooding are pictures in this collage of news stories from 2025. (Juneau Empire file photos, credits left to right: Jasz Garrett, Jasz Garrett, Chloe Anderson)
Juneau’s 2025 year in review

The Empire revisited eight major topics as their headlines progressed.

The Alaska Department of Transportation and Public Facilities, contracting with Coastal Helicopters, works to reduce avalanche risk on Thane Road by setting off avalanches in a controlled fashion on Feb. 5, 2021.(Michael S. Lockett / Juneau Empire file photo)
DOT&PF has a plan to reduce avalanche hazard near Juneau amid record snowfall

They’re set to fly over the snowpack above Thane in a helicopter at about noon to trigger a controlled avalanche.

A truck with a snowplow drives along Douglas Highway on Dec. 31, 2025. (Mari Kanagy / Juneau Empire)
Warnings pile up under record-breaking snowfall in Juneau

December 2025 is the snowiest December in the city’s history.

Alaska's Department of Transportation and Public Facilities issue a warning of increased avalanche hazard along Thane Road. (Juneau Empire file photo)
Avalanche advisory in effect for Thane, Downtown

The alert is not an evacuation notice, but officials urge residents to stay informed.

Emergency lights flash on top of a police car. (Ben Hohenstatt / Juneau Empire file photo)
Child dies in car accident on Christmas Eve, Juneau community collects donations

Flying Squirrel will serve as a collection point for donations for the child’s family.

Dense, wet snowpack piles up beneath a stop sign on Great Western street. (Mari Kanagy / Juneau Empire)
More heavy, wet snow forecast for the Juneau area this week

Capital City Fire and Rescue cautioned residents without four wheel drive from taking on the roads.

Photo by James Brooks / Alaska Beacon
Alaska Gov. Mike Dunleavy greets a child during the governor’s annual holiday open house on Tuesday, Dec. 12, 2022 at the Governor’s Mansion in Juneau.
Pipeline deal and disasters were highlight and low point of 2025, Alaska governor says

Alaska’s traditional industries got a boost from the Trump administration, but more drilling and mining are likely years away

Most Read