A photo taken from the terminal roof shows the extent of the first phase of paving to accommodate large aircraft. (Mike Greene / City and Borough of Juneau)

A photo taken from the terminal roof shows the extent of the first phase of paving to accommodate large aircraft. (Mike Greene / City and Borough of Juneau)

Large-scale repaving project plants itself at Juneau International Airport

Work may take two to three years, schedule seeks to limit impact on operations.

A complex repaving project of areas near the terminal at Juneau International Airport is underway using an onsite asphalt batch plant to increase efficiency, according to officials.

The temporary batch plant began operating at the east end of the airport soon after the City and Borough of Juneau Planning Commission approved the operating permit at its Tuesday, May 14 meeting.

“The plant will operate during the construction season of April through October for the next two to three years,” said Airport Manager Patty Wahto in a May 17 phone interview.

“Locating the facility on airport property reduces the traffic on public roads from the large dump trucks hauling asphalt from another site,” she added. The batch plant will serve airport needs solely.

A temporary asphalt batch plant located at the east end of the Juneau International Airport is permitted to operate April through October until 2026 to replace pavement surrounding the airport terminal and some secure aircraft parking areas. Discreet phases are scheduled to minimize disruption of airport operations. (Laurie Craig / Juneau Empire)

A temporary asphalt batch plant located at the east end of the Juneau International Airport is permitted to operate April through October until 2026 to replace pavement surrounding the airport terminal and some secure aircraft parking areas. Discreet phases are scheduled to minimize disruption of airport operations. (Laurie Craig / Juneau Empire)

Airport Project Manager Mike Greene is overseeing the paving project which will cover surfaces, or aprons, around the terminal. Runways are not being repaved.

“Asphalt wears out and we have to replace it,” he said on Friday about the paving work being done.

A key new section is being added for large aircraft to park overnight. Heavy planes cannot rest on asphalt for very long periods because their weight is normally concentrated on only three points of contact.

“Asphalt is soft and a plane can sink a bit into the asphalt,” Greene said, which is why there is a “hard stand” area of concrete atop several inches of asphalt for bigger aircraft to “remain overnight,” a term coded as RON.

Having the asphalt batch plant on airport property has an advantage in addition to reducing truck traffic on local highways. The fresh asphalt allows a “hot joint” to fuse side-by-side pavement strips which provides a better seal between sections. Cold joints, caused by farther transport of hot asphalt from a batch plant, shortens the life of the paved junctions.

Sunny weather on Tuesday, May 21, provides ideal conditions for paving. A helicopter with Juneau Icefield tour passengers takes off nearby. (Laurie Craig / Juneau Empire)

Sunny weather on Tuesday, May 21, provides ideal conditions for paving. A helicopter with Juneau Icefield tour passengers takes off nearby. (Laurie Craig / Juneau Empire)

The plume of dust and heat rising into the air attracted commuters’ curiosity in mid-May when the plant cranked up its fiery operations of heating gravel and tar to bond as asphalt. Drivers have noticed large gravel piles accumulating at the east end of the airport near TEMSCO’s helicopter hangar. When operating, the plant feeds gravel by conveyor belt into a hot rotating cylinder where heated tar mixes to form asphalt that will be carried a short distance by dump truck to be lifted into paving machines that lay and compact the hot surface. Heavy rollers further compact the asphalt. Several layers are necessary to build solid support for large aircraft.

To minimize the impacts on busy airport functions the paving work will be performed in discreet sections. Color-coded illustrations of the various enumerated phases of paving are available on the airport’s website at www.juneau.org/airport. Check the monthly Project Manager’s reports for details.

An important deadline to have certain paving completed is June 7 when Delta Airlines’ first jet of the summer arrives.

Weather can impact the project. Days of heavy rain delay or postpone some paving when accumulated pools of water prevent proper bonding of asphalt layers. Conversely, when fair weather prevails work increases. Crews put in two back-to-back 17-hour days on Tuesday and Wednesday before heavy rain fell on Thursday, slowing progress.

Dark asphalt is laid and compacted near an area where large aircraft can remain parked overnight at the airport. (Laurie Craig / Juneau Empire)

Dark asphalt is laid and compacted near an area where large aircraft can remain parked overnight at the airport. (Laurie Craig / Juneau Empire)

Additional improvements to the airport exterior are planned for summer 2024. Some passenger boarding bridges — also known as “jetways” — that provide passenger loading and unloading will be replaced. Embarkation and debarkation will shift slightly to other nearby areas.

“The airport will stay fully operational during paving and construction,” said Ke Mell, the airport’s architect. She said finishing touches are still being completed inside the renovated terminal as well. Some glass panels are being installed behind temporary sheets of protective plastic suspended from the ceiling. She pointed to the new seating in the secure area departure lounge which can accommodate almost all the passengers from four jets simultaneously if needed. Gone are historic item display cases and circular seating arrangements that reduced space for seating.

Other paving projects around the city planned for this summer will likely rely on the Lemon Creek asphalt plant. Douglas Highway and 10th Street in Juneau are scheduled for renewed road surfacing.

• Contact Laurie Craig at laurie.craig@juneauempire.com.

More in News

Mount Juneau stands among fog on Jan. 14, 2025. (Chloe Anderson / Kenai Peninsula Clarion)
CBJ lifts all avalanche evacuation advisories for Juneau

That includes the advisory for the Behrends slide path, the last remaining evacuation notice.

Juneau Jazz Fest founder Sandy Fortier will be leading Alaska Arts Education Consortium. (Alaska Arts Education Consortium)
Juneau Jazz Fest founder to lead Alaska arts consortium’s education efforts

Sandy Fortier, now AAEC executive founder, was a Juneau music teacher

A City and Borough of Juneau map from 2021 shows labels four avalanche slide paths on Mount Juneau. (City and Borough of Juneau)
Avalanche hazard on Behrends path to peak late Tuesday, CBJ says

‘Likelihood of large avalanches’ could significantly increase during that time, advisory warns.

A City and Borough of Juneau map from 2021 shows labels four avalanche slide paths on Mount Juneau. (City and Borough of Juneau)
Evacuation advisory in effect for Behrends slide path, all others lifted in Juneau

Avalanche hazard is still high across all known slide paths, CBJ says.

A map from the City and Borough of Juneau shows the potentially impacted area of an avalanche advisory that was issued Friday morning (Jan. 9, 2026) (City and Borough of Juneau)
UPDATE: Thane Road reopened, “Hazard is still high” for downtown avalanche

Avalanche risk remains high, and more rain is expected through tomorrow evening

A map from the City and Borough of Juneau shows the potentially impacted area of an avalanche advisory that was issued Friday morning (Jan. 9, 2026) (City and Borough of Juneau)
UPDATE: Downtown Juneau residents in slide zone advised to evacuate amid avalanche risk

Emergency shelter will be available at Centennial Hall by noon.

Capital City Fire Rescue is asking Juneau residents to dig out fire hydrants near their homes and businesses as heavy snow continues. File photo
Capital City Fire Rescue asks Juneauites to clear nearby fire hydrants

Clearing a three-foot radius can “save precious minutes in an emergency.”

The National Weather Service has issued a flood watch for Juneau Friday (Jan. 9, 2026). (NWS)
Flood watch in effect for Juneau

The National Weather Service warns that snowpack blocking storm drains may cause ponding on roadways.

A snow pile sits outside Thunder Mountain Middle School. Juneau School District has cancelled school Friday Jan. 9, due to hazardous road and weather conditions as an atmospheric river arrives. (Clarise Larson / Juneau Empire file photo)
UPDATE: Schools closed in Juneau Friday, potential for remote learning next week

Flood watch in effect through Saturday night for Juneau and much of the Southeast.

Most Read