A hearing officer heard arguments for and against revoking a special use permit the city granted for a Central Council of the Tlingit and Haida Indian Tribes of Alaska-run transitional living facility on the corner of Alaway Avenue and Glacier Highway. This picture shows a proposed design of the facility. (Courtesy Image / Tlingit and Haida)

Hearing held for proposed Alaway Avenue project

Both sides of debate make their case.

Opponents of Central Council of the Tlingit and Haida Indian Tribes of Alaska’s plan to build a transitional housing facility for people recently released by the Department of Corrections made their case to reverse the city’s decision to allow the project in a Zoom hearing Monday evening.

An attorney for Tlingit and Haida said the project fills a critical community need and should be allowed to go forward. The City and Borough of Juneau defended the permitting process that cleared the way for the development.

Concerns center around plans to build the facilities at 6205 Alaway Avenue, near the police station. CBJ issued a special use permit over the summer, allowing the development in an area zoned for industrial use. The city accepted an appeal against the permitting of the facility in the fall based on community concerns.

Opponents of the plan say the Planning Commission approved the request for inappropriate reasons and based on incorrect findings. They cite a concern about sex offenders at the facility and its proximity to a school and school bus stops.

Both CBJ and Tlingit and Haida said that the facility would not serve as a destination for sex offenders.

CBJ officials also said that the Planning Commission followed all the rules for public notice and hearings and that not liking a decision is not a reason to reverse it.

City accepts transitional housing appeal

Making the case

“We are here to address a mistake made by the Planning Commission,” Lemon Creek resident Shawn Wille told Ketchikan-based hearing officer Scott Brandt-Erichsen. “This location is in a school zone, a very busy school zone.”

Keri Weldon, who was part of the appeal, said that the decision was made too quickly.

“This was a dangerous and reckless decision recommend by development staff. It was bulldozed through because CARES money must be spent. The decision is based on inadequate facts,” Weldon said.

Weldon and Wille said that the facility is in a school zone near Dzantik’i Heeni Middle School and that although Tlingit and Haida say that sex offenders will not be eligible to apply for the programs there, CBJ lacks the authority to enforce that rule.

They said the neighborhood is “diverse and socially and economically challenged” and the wrong location for the facility.

“We talked to all kinds of entities about this facility, and everyone said red flags, red flags, red flags,” Weldon said. “I think this is insane.”

Tlingit and Haida works to bring transitional housing projects to life

CBJ: All rules were followed

Sherri Layne, assistant municipal attorney for CBJ, said that despite statements by Weldon and Wille, the decision was well researched and well thought out.

“The Planning Commission did its job here,” Layne said. “They evaluated all the evidence.”

Layne said that city staff provided notice of the Planning Commission’s meeting following CBJ code, including mailing notices to residents a month before the meeting and positing signs about the affected neighborhood’s hearings. She said that an additional step was added to the process that included a neighborhood meeting coordinated between Tlingit and Haida and the city.

“The notice worked. We got 58 comments on the development,” Layne said. She added that Weldon and Wille had both participated in the hearings, which shows that the hearings were public and publicized.

“Mr. Wille and Ms. Weldon both submitted correspondence. The Eagles Ridge homeowners submitted a letter. It was all in accordance with code,” Layne said.

“This was not fast-tracked or bulldozed. The commission followed normal protocol for meetings,” Layne said, noting that the public meeting was conducted by Zoom. “The commission did not take their job lightly. The record shows that they did their job. They read all comments.”

Meeting a critical need

Kendri Cesar, an attorney representing Tlingit and Haida at the hearing, said the facility meets a critical community need.

“Supportive housing is critical for re-entry,” Cesar said. “The project allows the opportunity to reduce recidivism and improve public health as it’s not a congregate setting,” she said.

Cesar said the facility is modeled after the successful Haven House development and will be staffed with professionals and enforce house rules to support recovery.

“There is no crystal ball to recidivism, but there is the possibility of beautiful success stories. We are committed to resident success,” Cesar said.

Cesar told Brandt-Erichsen that the evidence shows that all procedures were followed and that the permit was issued in accordance with all requirements.

“Despite their claim that the decision is not supported by evidence. There is substantial evidence. Just because the appellants disagree with evidence doesn’t mean it’s inadequate. The appellants want a second bite at the apple to get a different result,” Cesar said.

Sex offender concern

One of the primary concerns expressed by Wille and Weldon centered around the idea that sex offenders could live in the facility and that CBJ has no mechanism to revoke the facility’s permit or stop the practice once it starts.

“The CBJ needs regulation, like a means to revoke the permit when bad things happen,” Weldon said. “We can’t assume that they will never have a sex offender there.”

However, according to Cesar, sex offenders are ineligible for consideration in the center’s programs, and there are no plans to add them in the future.

“It was stated over and over again that sex offenders would not be allowed in the facility. It’s part of the permitting process. Those convicted of sex crimes will not be allowed in the facility,” Layne said.

Next steps

Brandt-Erichsen said that he would draft and circulate a proposed decision “substantially before” the 45-day statutory deadline. The proposal will be circulated to all parties for a five-day comment process with three additional days to respond to comments. The city clerk will distribute the proposed decision when it’s available.

Contact reporter Dana Zigmund at dana.zigmund@juneauempire.com or 907-308-4891.

This photo shows a crosswalk near the site of a proposed transitional housing project on Alaway Avenue. The project has drawn criticism from nearby residents because of its proximity to routes children take to get to school. (Ben Hohenstatt / Juneau Empire)

This photo shows a crosswalk near the site of a proposed transitional housing project on Alaway Avenue. The project has drawn criticism from nearby residents because of its proximity to routes children take to get to school. (Ben Hohenstatt / Juneau Empire)

More in News

Jasmine Chavez, a crew member aboard the Quantum of the Seas cruise ship, waves to her family during a cell phone conversation after disembarking from the ship at Marine Park on May 10. (Mark Sabbatini / Juneau Empire file photo)
Ships in port for the week of July 13

Here’s what to expect this week.

(Michael Penn / Juneau Empire)
Police calls for Sunday, July 14, 2024

This report contains public information from law enforcement and public safety agencies.

Police and other emergency officials treat Steven Kissack after he was shot on Front Street on Monday afternoon. (Mark Sabbatini / Juneau Empire)
Steven Kissack, homeless resident known for canine companion Juno, killed in police confrontation downtown

Kissack shot repeatedly after coming at officers with a knife on Front Street, officials say

(Mark Sabbatini / Juneau Empire file photo)
Two people arrested at Juneau residence after receiving package with $65,700 of suspected illegal drugs

JPD: Drug investigators intercepted package, then delivered it after inspecting contents.

(Michael Penn / Juneau Empire file photo)
Police calls for Saturday, July 13, 2024

This report contains public information from law enforcement and public safety agencies.

(Michael Penn / Juneau Empire file photo)
Police calls for Friday, July 12, 2024

This report contains public information from law enforcement and public safety agencies.

(Michael Penn / Juneau Empire file photo)
Police calls for Thursday, July 11, 2024

This report contains public information from law enforcement and public safety agencies.

Residents of Strasbaugh Apartments on Gastineau Avenue and others in the neighborhood wait outside a sealed-off area Sunday morning after a landslide triggered by heavy rain hit the building. (Mark Sabbatini / Juneau Empire)
Landslide triggered by heavy rain damages apartment building on Gastineau Avenue

Officials close street as multiple mudslides reported; up to 4” more rain forecast by Monday night.

Shelley McNurney (right) and Tami Hesseltine examine a muticolor storage shelf in the gym of the former Floyd Dryden Middle School on Saturday, where surplus items from the school were being sold to residents and given away to nonprofit entities. (Mark Sabbatini / Juneau Empire)
No more pencils, no more bookshelves: Floyd Dryden works to clear out surplus items large and small

Furniture, microscopes, pianos among gymful of items being given away or sold by shut-down school.

Most Read