Local
Alaska Electric Light & Power Co. contractors were on schedule this week as they cleared the Snettisham avalanche path for new power line and transmission towers to go in, according to the electric utility.
Snettisham site readied for work on new towers 051108 LOCAL 4 JUNEAU EMPIRE Alaska Electric Light & Power Co. contractors were on schedule this week as they cleared the Snettisham avalanche path for new power line and transmission towers to go in, according to the electric utility.

Courtesy Of Aelp

Progress: A helicopter crew flies over a transmission tower earlier this month near the Snettisham hydroelectric plant.


William Boatman / Alaska Electric Light And Power Co.

Construction on schedule: Workers install new high voltage electric lines on a transmission tower earlier this month. The April 16 avalanches mangled and ripped out a portion of the high voltage lines that link the Snettisham hydroelectric plant to Juneau.

Click Thumbnails to View
Sunday, May 11, 2008

Story last updated at 5/11/2008 - 4:09 am

Snettisham site readied for work on new towers

Alaska Electric Light & Power Co. contractors were on schedule this week as they cleared the Snettisham avalanche path for new power line and transmission towers to go in, according to the electric utility.

The roughly $7 million project is still scheduled to be finished by mid-to-late July, according to Scott Willis, AEL&P's generation engineer.

"They had a good week," Willis said.

The first phase of the project is cleaning up the damage. An April 16 avalanche destroyed two towers, damaged five others, and disconnected the transmission line that supplied Juneau's hydroelectric power from the Snettisham lakes, 40 miles south of town.

Two crews of contractors from Anchorage-based City Electric Inc. worked on the mountainside last week, according to Eric Eriksen, vice president of transmission and generation.

They removed the high-voltage power transmission line from the towers and attached it to the ground. That way it can't drag structures down if there's another avalanche.

Helicopters took out downed tower parts. Friday, workers were shoveling out the last tower foundation still covered by snow. All the foundations are in good condition, Willis said.

Another crew, on flatter ground at Snettisham, assembled spare tower parts that until now have been stored there and at a Thane warehouse.

The new towers will be built on the foundations of the old ones. Helicopters will fly them in. The towers vary in weight from under 3,000 to about 12,000 pounds.

The last step in the project will be to restring the transmission line across the towers.

Two avalanche experts have been watching site safety. Avalanche areas have been off limits at times, but the workers have been able to get to all the parts of the site, Eriksen said.

An avalanche came down Tuesday while workers were on other parts of the mountain.

"It was a little scary for everybody, because it reverberates throughout the area. But everyone was out of the path of damage," Eriksen said.

He said the site has been bustling. The 12 linemen and seven other support workers have been sleeping at the site. Plumbers, electricians, surveyors and other workers have been in and out on barges, helicopters and planes.

"My job is to make sure it's all in motion, and it's definitely never a dull moment," he said.

• Contact reporter Kate Goldenat 523-2276 or e-mail kate.golden@juneauempire.com.


Classifieds






Top Jobs

Loading...

Top Homes

Loading...

Top Rentals

Loading...

Top Boats

Loading...

Top Autos

Loading...

Top Jobs

Loading...

Top Homes

Loading...

Top Rentals

Loading...

Top Boats

Loading...

Top Autos

Loading...



Facebook
Twitter
News
Share
Shop
Life
Visit