Archives
In preparation for spring snowmelt, Coeur Alaska has asked the 9th Circuit Court of Appeals to allow construction of a drainage ditch near Lower Slate Lake at the mining company's Kensington mine site 40 miles north of Juneau.
Coeur asks permission to build ditch for snowmelt 031107 local 4 JuneauEmpire In preparation for spring snowmelt, Coeur Alaska has asked the 9th Circuit Court of Appeals to allow construction of a drainage ditch near Lower Slate Lake at the mining company's Kensington mine site 40 miles north of Juneau.
Michael Penn / Juneau Empire
  Overview: Snow covers Lower Slate Lake, right, with Berners Bay in the background. Coeur Alaska has asked the 9th Circuit Court of Appeals to construct a diversion ditch at the lake in preparation for spring runoff.

Coeur asks permission to build ditch for snowmelt

Company barred from construction pending court ruling

In preparation for spring snowmelt, Coeur Alaska has asked the 9th Circuit Court of Appeals to allow construction of a drainage ditch near Lower Slate Lake at the mining company's Kensington mine site 40 miles north of Juneau.

Print This
E-Mail This
Send editor a comment
Sound off on the important issues at
Coeur is barred from most construction activities at the lake pending a ruling on a lawsuit by the Southeast Alaska Conservation Council. The group has contended that the mine would violate the Clean Water Act if allowed to dump its mine tailings - as it has proposed to do - in the lake.

Coeur wants permission to construct a diversion ditch at the lake in preparation for spring runoff. The ditch would serve as backup to a temporary coffer dam constructed during the summer of 2006. Overflow water would be diverted into Slate Creek.

The U.S. Army Corps of Engineers has approved the ditch. In a request to the court, it estimated that it would take about 48 days to finish the ditch in favorable conditions.

It also said that runoff flow could begin as early as April.

SEACC worries that there's not enough time to dig the ditch properly and that it could cause water quality problems. It claims the mining company failed to plan adequately, saying that it has known since August to prepare for spring snowmelt.

"The time frame just doesn't add up if Coeur is really concerned about water quality," said Rob Cadmus, SEACC'S mining and water quality organizer.

"Even if the court authorizes construction of the ditch, Coeur couldn't complete construction before the spring runoff starts," he said.

"Was Coeur gambling that it wouldn't snow in Berners Bay this winter?"

"We have been working with relevant agencies to make sure that they knew what we were doing, and we certainly took our time to do it right," said Scott Lamb, a spokesman for the Idaho-based mining corporation.

"I think you can assume that we wouldn't be proceeding at this point unless we thought it would be done in time to prepare for runoff," he said.

SEACC also said, however, that two federal agencies - the Environmental Protection Agency and National Marine Fisheries Service - have suggested viable alternatives to the diversion ditch that would have less of an impact on waterways.

These included building a spillway on the coffer dam, improving erosion control measures, or adding more water pumps, SEACC said.

The conservation groups says the ditch proposal is part of Coeur's plan to develop the lake by reducing costs associated with treatment of polluted water.

Lamb said that the diversion ditch is designed only to handle runoff during this period of inactive construction.

He said experts at Coeur and the U.S. Corps of Engineers were confident that this plan was the best way to prepare for the spring melt.

Coeur had requested the court to remove the injunction restricting construction activity at the lake on Nov. 7, 2006. That request was denied in December.

• Brittany Retherford can be reached at brittany.retherford@juneauempire.com.



AP Video and News

Updated 1:05 AM ET
Former NFL quarterback McNair killed in Tennessee
More than 1 million seek tix for Jackson memorial
Palin links resignation to 'higher calling'
NYC fireworks highlight US Independence Day events
Exiled Honduran president vows return on Sunday
Obama's trip: A mission to reshape US image
Missiles show NKorea skills improving: officials
More News

Classifieds






Top Jobs

Loading...

Top Homes

Loading...

Top Rentals

Loading...

Top Boats

Loading...

Top Autos

Loading...

Top Jobs

Loading...

Top Homes

Loading...

Top Rentals

Loading...

Top Boats

Loading...

Top Autos

Loading...



Twitter
News
Share
Shop
Life
Visit